Friday, December 18, 2009

Mud becomes rock


The last week hasn't been one to write home about. The earthen walls behind the new concrete walls continued to deteriorate. My task was to excavate around the form-a-drains and shovel in crushed stone along their outsides so no soil was in contact with them and crushed stone could be dumped on top of them. This would provide a clear path through the crushed stone through which water could drain keeping it off of the concrete walls.

By early this week I had dug along the wall footings and replaced soil with stone, a length of 116 feet, except for about 15 feet at the west end of the master bedroom wall where it meets the bathroom wall.

In that area the soil was so wet it just oozed from the wall toward the footing at about the consistency of cake mix. As fast as I could muck it out it replaced itself. Worse, there was no practical place to toss what I was able to pick up. It had to be carried in buckets all the way around to the east wall, or west to at least the laundry room wall. Dropping it against the earth wall near where it came from just caused it to fill in faster.

The space was barely large enough to walk through. No mechanical equipment could get to it because the wall sections are each too short to reach into with a backhoe or other large shovel.

I spent the better part of two days trying to deal with it. It was a nasty job and I'm glad it's finally over.

Freezing weather actually helped by slowing down the water flow and freezing the mud. Also, all day Wednesday, Sandy cleaned out the trenches on both sides of the lower frost footings while I lined them all with polystyrene.

Here's what the wall "canyons" looked like looking west after sunset Wednesday evening. Visible along the wall is a "clean" section of the polystyrene-covered footing. Just past that, beyond where the shovel is standing, is where the mud slurry begins. It's eerie, isn't it, seeing the tree roots hinging along the edge?



My contractor guru, Dick Stumpner, suggested we just abandon the form-a-drain and install another drain on top of the footing against the walls. This new drain is wrapped in a sleeve to exclude soil which might eventually filter through the stone and clog it.

This approach still required the footings to be cleared, but only down to the footing tops and only a bit wider than the new drain, 6 inches or so. More was better, but in a few areas, considering the muddy soil, the drain width was the best we could do.

Much of the wall length had already been cleared by Thursday morning when the excavating team arrived and we started unrolling drain pipe almost at once. Stone was delivered and they began to dump the crushed stone over the walls onto the pipe. We covered it a foot or two deep to hold it down as we progressed around the wall, digging out a bit of soil here and there to allow the pipe to lay flat on top of the footing.

By the end of Thursday we had all the drain pipe in, from both ends of the wall, to within about 20 feet of each other. Today we worked for about two hours to clear the last 20 feet.

We were able to get a backhoe above the northeast corner of the walls and use it to scrape out most of the north section behind the master bedroom wall. Then stone was dumped over that section so we'd have a place to pile muck from the problem area. Not too long after that the two drain sections were connected.

We spent the rest of the day dumping stone over various wall sections and spreading it into the corners that the backhoe bucket couldn't get close to. Here's what it looks like now.


Weather permitting, we'll pick it up again on Monday morning.

Monday, December 7, 2009

Clearing the footing drains


About the time the concrete walls were finished some of the earthen wall behind them caved in. At some places the fallen material covered the new footings and the outside drain form with heavy clay. To be sure this does not inhibit water behind the wall from draining away, I have been shoveling a trench at least 8 inches wide next to the drains and down far enough to expose the slits in them that allow water in. Then I'm filling the trench with gravel to be sure there will be a path for water when the backfill is added or in case more caves in before the fill is added.



We had snow on the ground this morning so I did some things in the apartment all day. There's a good chance of rain in the morning and for the next few days, up to a half inch or more.

I hope to get the rest of the clay and mud off the drains despite that because it's forecast to be as cold as 12 degrees before the weekend. I might have to lay some of the polystyrene panels over top of the canyon if I have to dig while it's raining. The temperature is forecast to be in the low 40's, not bad for this time of year.

Malcolm Wells, Pioneer of Underground Housing, 1926-2009


Sometime in the last ten years I learned about Malcolm Wells. Soon after I got ahold of one of his books. It is full of good sense and humor.

With no offense intended to friends and relatives, here's just a small fragment of his philosophy of building:

"We live in an era of glitzy buildings and trophy houses: big, ugly, show-off monsters that stand--or I should say stomp--on land stripped bare by the construction work and replanted with toxic green lawns. If the buildings could talk they would be speechless with embarrassment..."

Mr Wells died on November 27th at age 83. I wish I could have met him and I encourage you to visit his web site. You will not be disappointed. It is full of his ideas and sketches of various underground buildings. The web site was created and maintained by his fans since he never really seemed to grasp the internet.

After seeing the damage that our new house is doing to the hillside, I feel like a hypocrite when I recommend his works. I hope we can restore the landscape as closely as possible to what it was and end up with a home that allows nature to reclaim most of the surface it covers.

Maybe not too much work today


This picture through the warm apartment window speaks for itself.

2 days old and already sinking


Or maybe the camera is just tilted.

Now that the walls are done it's time to insulate them. I'm using 2 layers of 2-inch extruded polystyrene on the walls and one layer on the tops of the footings. Two layers will provide an R-20 insulating value.

You can see some of the insulation already placed in this picture.


The strange figure in the window below is working on clearing the form drains.


Could he be the Travelocity gnome?

Friday, December 4, 2009

Concrete - Video


Enough of the still pictures. Here's a scan of the finished footings and walls.



When the concrete floor is poured it will be level with the top of the short wall in front. Most of that wall will be underground with the top just an inch or so above the patio level

Concrete - Day 4


It was a short day. The crew came early, knocked out all the connectors, took down all the forms, lifted all the cages of forms back onto the truck, cleaned up and took off. I barely had time to take any pictures.

Here the outside forms have already been removed and lifted over the wall. The walkways at the top of the inside forms have been removed and some of the cages have already been reloaded to the truck.



They left two guys behind to spray the outside of all the walls and footings. One is handling the hose at the top of the wall while the visible one is spraying below. Some of the waterproofing is visible on the wall section to the right.



I took off to buy the first load of insulation panels which will go up two thick - 4 inches, giving us R-20 insulation on the outside of the concrete walls. They were gone by the time I got back.

Thursday, December 3, 2009

Concrete - Day 3


Our third day of the concrete work was much nicer than anyone had expected. It rained 7/10ths of an inch overnight which turned our polystyrene-lined frost footings into miniature canals. But, as the day went on, the temperature rose and, except for the mud mostly outside the building's footprint, it was a pleasant working environment.


The crew knocked out some of the polystyrene that protruded above the footing and dug a small trench at each end of the south wall.

The trench on the east side directed the muddy water into the low area between the dirt pile and the original slope of the hill. This ran down and into the drain I had laid last week under the path below. The drain worked great and the ponds were filling up.


You can see why I need to raise the height of the upper pond's overflow pipe. The water level could be much higher without jeopardizing the pond.

The crew set right to work setting forms on both sides of the rebar that had been placed and tied the day before. While they were doing that the rest of the wall sections' reenforcement was cut, bent and tied into the bars embedded in the footings.


The forms were going up quickly, though some corners on the outside had become tighter to work in than the day before. The chunk of soil and rock seen here is the largest to have broken off along the back wall, but there were lots of other smaller pieces and some parts of the walls were dripping with runoff from above.


The forms they used have a brick pattern. We will be covering most if not all of the interior wall, so the brick facade will be unseen when the house is finished, but it will look interesting in the mean time.

By this time the concrete pump arrived. What an enormous machine! By the time they got it into place and ready to go, there was hardly any driveway left. Huge ruts were created and a few more trees bit the dust.


By then the walls had been braced, a working ledge had been installed along the top ...


and the window block-outs were in place, so they were ready to start pumping.


The boom on the pump had four large segments. When it is deployed it looks somewhat like a gigantic grasshopper.


As the pump's outlet moved along the wall, John followed along with a long concrete vibrator that reached to near the bottom of the forms to encourage the concrete to fill all the nooks and corners of the forms.


The forms for the stem wall are shorter, of course, so they go together more quickly, and they require very little rebar compared with the 9-foot walls. Sitting on the footing is a section of plastic pipe that was embedded in the wall for the drain to the septic system. Tubes were also placed for incoming water, electricity and telephone. These were covered with duct tape to be knocked out when the forms come off.


Here's a view from the hillside above. Progress continues on the pumping, even as work is still going on on the frost footing wall around the greenhouse.


The crew was very efficient and little time was wasted. It seemed everyone was adept at every job so there was never any waiting for the "right" person to get something done. If anyone needed help, the next person along could be drafted for any task.

Wednesday, December 2, 2009

Concrete - Day 2


The weather is turning nasty later today. It was cool at 8 am, but not as cold as yesterday started.

The crew arrived with an enormous truck loaded with heavy forms for the concrete walls. The truck is very long. Amazingly, they were able to back it in almost all the way. As it was being backed up the last 30 feet toward the east wall, the slope was too steep and one axle was literally lifted off the gravel, so it had to stop there.

It's huge outriggers, visible in the picture below, were deployed and the truck was leveled side to side.

The forms are stored in large cages each of which weigh about a ton. The truck has a large crane/boom on the back. It can lift the cages up to 70 feet high and about that far away from the truck. As it was unfurled it reminded me of a kid's transformer toy.


It was so dark the camera's flash went off making the machine look like it's all lit up as light reflected from the ladder sides.

As the operator began to unload cages of forms, the rain started slowly. The guys finished marking the footings in preparation for setting up the forms and, as that effort was being finished, decided to call it a day.

They left the truck in place so they can get a running start after the weather improves. The forecast highs and lows from today through Sunday are 43°/32°, 40°/23°, 34°/20°, 38°/22°, and 41°/27°. Rain and snow are both in the forecast, so it's up to the concrete crew to decide when to finish up.

Tuesday, December 1, 2009

What a difference a day makes


The concrete crew, A & D Construction from south of Odon, Indiana, came at sunrise and left at moonrise and a beautiful full moon it was.

All of our footings were formed and poured in one long day. First, the above-grade forms/drains were placed. This part of the site was under about three inches of water because very thick chunks of hard clay had come out during excavation leaving more depth than desired. Crushed stone had to be placed on both sides of all the above-grade footings. The footing depth here was to be 10 inches so the forms were three inches above the established grade. This left one inch for a layer of extruded polystyrene.


As the forms were finished, extruded polystyrene sheets were placed on the bottom and both sides of the formed space and reinforcing bars (rebar) were placed and tied together on metal lifts called chairs.


By this time the first concrete truck had arrived and they started pouring concrete. I found this situation almost comical as they were pouring concrete on one end of a wall section even before the rebar was all placed and tied at the other end. This picture shows concrete oozing toward one of the guys as he was racing to get the bars tied to the chair.

Twisting wires around the bars is a time-consuming operation, but he was using a tool, visible in his left hand, that grabbed two or more bars and wrapped and twisted them together with wire from a spool inside the tool. Just in front of his knees, if you look carefully, you can see one of the chairs that keep the rebar elevated as it is covered with concrete. It looks like two small ladders in a triangle, like a few pup tent frames side by side.


Most of the back wall segments are complete in this picture. Five or six guys are working constantly as the concrete is placed, plus the truck driver.



Up to this point the concrete trucks were able to pull all the way into the future living area. This was possible because the last wall along the east of the future kitchen area was not dug until all the other walls were poured. Here the guys are cleaning up the bottom of the footing trench under that wall so the polystyrene will lie flat in the bottom.

The footings are at two levels. Those under walls which will be under ground more than a few feet are formed above ground. These are the ones that have been shown so far. This trench is deeper than the frost line. Footings at this level will have a short wall on them that will bring concrete up to the level of the floor slab.

In the background we have spread multiple billboard tarps that extend about 20 feet up the hill to where a small hill of soil diverts rainwater from farther uphill to the building's sides. Water falling on these tarps, if all goes well, will fall harmlessly behind the footings without mud, clay and rock calving off the walls.


This view shows the greenhouse area. It looks like an island. The below-grade footings do not need forms since the earth does a darn good job of stopping concrete. The "walls" are very wavy because the soil came out in big sticky globs. As long as there is a straight area wide enough for the short walls, the footing is adequate. We also lined the trenches with polystyrene. A laser level sits on its tripod inside the greenhouse area.


Looking from the southwest corner to the northeast corner, a distance of about 72 feet.


Looking west to east. The final concrete truck is coming into view to pour the final 60 feet of sub-grade footing.

Tuesday, November 24, 2009

Placing rocks


Yesterday I recruited our neighbor and his tractor to move the big rocks that were pushed down the south bank of the new pond. One was actually too large to be dragged (without leaving an enormous trench in the wet area) and was left where it had fallen.

This picture shows them scattered across the wetland area. They were not too carefully placed in the hopes it will look more natural that way when the plants grow up around them. They also are not very flat, so it will still be a challenge to hop across them. The smaller ones were placed by hand. A few more will be added to be sure everyone can get across dry if they try.

Ruts we made can be seen on the right side of the rocks so I still need to use a hoe or shovel to fill in a few of them and to cut some small slots where the ruts are running across the flow of the stream so the water won't pool up anywhere. Let's see what it looks like in the spring.

And today, while I was spreading grass seed and covering it with straw, I found this little guy who didn't seem to care that I had disrupted the wetland by dragging rocks through it.

Monday, November 23, 2009

A better perspective?


It's hard to find a perspective that shows where everything is in relation to the others. Here's a shot that Sandy took from the far side of the wetlands area.

The light green below the white-barked trees is the wetland through which the spring water drains, west (left) to east (right). It has a large colony of mint whose aroma is very strong when it is bruised by walking through it. Sometimes a breeze will carry the mint aroma toward the ponds.

One can see Brian and me inside the larger pond. The south side of the dam has a very large rock in the middle at its top. Just above that in the picture (though actually about 30 feet north) is the large rock on top of the smaller pond's overflow pipe.

Below the rock on the larger pond's dam, on the outside, we have pushed a half dozen or so large rocks to the bottom, out of sight. They are way too heavy to be moved by hand. I hope to get help from a neighbor and his tractor to drag them southward into the wetland so we will be able to rock hop through it without damaging plants or leaving a trail. As it is now we cannot easily cross it much of the year because of the running water.

The light blue spot is a small storage "building", and I use the term loosely. It is just straw bales piled on either side of two side-by-side pallets, covered with a few tarps. This gives us a very temporary dry place to store tools without having to cart them up and down between the barn and the house site every day.

To its left, above and to the left of where we are standing, is the huge pile of dirt and clay excavated from the house site. It has completely overtaken the hillside below the house.

Between and behind it and the temporary building the excavated earthen wall can be seen.

Remember, all construction photos are at http://picasaweb.google.com/ed.paynter/NewHomeConstruction#, even the unflattering ones.

Sunday, November 22, 2009

Manual labor crew


Today Brian came down from Indianapolis to help me work on the new ponds. This series of pictures requires more than usual explanation.

In the first, behind me, one can see the south side of the larger pond. If you click on either of the first two and look very carefully, you might be able to make out the thin yellow string along the top of the dam. Though it may not appear so, the string is level. Eventually the top of the dam will be leveled and parallel with but not all the way up to the string.

Notice the water that is still in the bottom of the pond. It might not be necessary to line these ponds since there is so much clay and it seems to be holding.

In the first two pictures we are working on a spillway of sorts that will allow rain water to flow into the bottom pond if it comes off the small hill to the left or off of the east end of the trail that passes above them.

The shiny soil under my feet is a finished stretch of the spillway. If the lower pond gets near to full this area will be under water.

Brian is touching a large rock somewhat smaller than a few we moved on the south side of the spillway. I am tromping on the outside of the upper dam which is also the north side of the lower pond. Next to the rock, though expertly hidden by the crew, a corrugated pipe has been buried to allow water that flows over or along the trail to enter without eroding the upper dam's lower wall.

The clay is not as mucky as it was just two days ago so it did not stick to the shovels much. With two of us working it was easy to raise the dam walls, one placing shovels full of clay while the other pushed and stomped it into place before it could roll down the embankment. Before, with one person working and the soil sticking to the shovel, placing it successfully on top of the dam was nearly impossible.


This last picture shows a wider view of the two ponds. From the top one can see the edge of the trail along the north side, a small trough filled with rocks to encourage drainage from above the trail to enter the upper pond, a line of larger rocks delineating the west side of the pond, the upper pond itself, the overflow pipe into the lower pond covered with a large rock that was placed by the backhoe, and the outline of the lower pond with the crew in it.

I have a pretty complete idea about how to finish off the ponds' walls, inlets and overflows. Early in the spring I'll seed the outside dam walls. After seeing these pictures, though, just one thing still puzzles me: Where the hell has all my hair gone!?

Saturday, November 21, 2009

Draining the site


Two posts ago I showed the puddles that have formed on the site after 7/10ths of an inch of rain. Some of that water has evaporated and some has sunk into the soil, but most is still sitting there. Today I scraped a small trench across the future bedroom, hallway and kitchen to get the water to flow out on its own.

The trench runs past the pile of dirt on the left and off down the hillside. It seems to be working. The water level is already falling.

The site is still very muddy, but not as bad as just after the rain.

Tracks


Since the hillside has been partially removed and a huge pile of dirt and clay is covering a lot more of it, one or more of the paths that deer have probably used for years is no longer there. This has caused at least one of the deer, and a rather large one by the looks of the tracks, to adjust his daily route to below the large pile on the hill and onto the part of the trail below the house site that has been raised with some of the dirt from above.

Here are prints laid down over two days, one track each day. They lead off into and through the middle of the larger, lower new pond. There are also tracks in the mud at the house site. I hope the deer will still pass below the house frequently after we move in.

Tuesday, November 17, 2009

Puddles


Work on the excavation was finished on Friday morning, mostly fine tuning a few spots on the walls and floor. It was a tiring week. Though I didn't operate any of the equipment, I was on the site from 8AM through at least 6PM every day.

Before the equipment was removed, a slight slope was graded at the front to deal with runoff from rain that falls before the footings are excavated. Footing excavation has been postponed until closer to the date the footings will be formed so we won't have a footing moat around the site.

I've been able to sleep late a few days in a row since then and don't feel nearly so tired as last week. I've been working on hand grading the two new ponds we built with the spoil from the excavation and burying some drain pipe into and out of the ponds.

We had a great run of good weather but that has come to an end. It began raining last night and we have a half inch so far. This has caused puddles to form on the house site.

The large puddle covers parts of the master bedroom, bathroom and hallway.

This is a view through the kitchen, living room and all the way to the guest bedrooms. It's very muddy but no pools are forming so far.

Seen to the extreme left is the edge of a huge mound of dirt. We hope most of it will be used to backfill behind the walls over the drains and stone that will be placed first. Frankly, I don't know what we'll do with any that is left over. We have already filled more area in front of the site than I had planned and I don't want to cover any more of the original surface.

Almost every inch of the site and everywhere the mostly clay soil has been moved and stockpiled is now sticky mud. As I walked across a section of the path below the house that has been raised with excavated soil, my boots picked up a few inches of mud. On the other side of the raised section where the path again is covered with wood chips, the mud picked up another half inch or so of chips. I was getting taller by the step.

The first pond below the path hasn't taken on any water yet. The larger pond below is beginning to fill with water. When the rain is over for a while, tomorrow or Thursday, I'll post some pictures of the ponds.

Thursday, November 12, 2009

all day, and all through the night...


The excavation continued today with a piece of rented equipment added to the backhoe and dozer. After many attempts to remove some very hard rock over the last few days with only very minor success, we rented a hydraulic rock breaker, basically a large jack hammer operated like a backhoe except it is on the end of a boom.

Here's how it works. Cover your ears.



Scintillating, eh?

Scott worked with this machine all day long and well after dark. First he drilled on the limestone. Then, while the rubble was being scraped away with the dozer or backhoe, he cleaned up another part of the excavated wall. Earlier in the day, the walls were marked with spray paint to show where they needed to be trimmed. The paint marks looked like cave drawings.


He switched between the wall and the limestone, back and forth, while someone else was cleaning up behind him.

This continued until about 7:30, almost two hours past sunset, since the rented machine needs to be returned tomorrow morning. About 6:15, it became clear that we would be there all night and still not remove all of the limestone.


I took a chance that my structural engineer might be in his office and called him to discuss the situation. Luckily, he was there.

I suggested that we could stop chipping away rock when we got it down to the level of the top of the footing to be poured. Then we could taper the footing when it came to the rock and continue it on the other side. He agreed that that would work if we connected the footings on either side of the rock with arched reinforcing bars embedded into each footing. These would be tied to a few bars drilled into the rock and the rebar in the wall when it is added. Additionally, the footing could be widened on the wall's outside. His only concern is that we take extra care to seal the connection between the rock and the concrete to prevent moisture seepage.

There are more pictures on my web album: http://picasaweb.google.com/ed.paynter/NewHomeConstruction#

Wednesday, November 11, 2009

Excavation - Day 3: Big rocks


We're on the third day of excavation and the big rocks are slowly being chipped and scraped away. Here's a mid-day video. Caution, the volume is high.

Tuesday, November 10, 2009

Excavation - Day 2


Contrary to the forecast, there was no rain at all last night nor today so a lot of progress was made on the home site.

We got the perimeter staked more accurately and then set all the stakes out another three feet. This leaves room for the concrete crew to work on the outside of the walls when they set up and remove their forms. Since the walls will be nine feet high above the footings, it can be pretty claustrophobic if there isn't enough room between the walls and the soil on the north side.

These two pictures show the same part of the project from two different angles. Sorry they are dark. They were taken just after sunset.

We have found a vein of heavy clay that can barely be broken with the dozer. When it is broken it comes up in sections, some as large as 15 to 20 square feet.

We have been saving the stones that were found near the surface for use in retaining walls near the front door. The large blocks we're getting out now are so numerous there aren't enough useful places to put them so they're being pushed downhill toward the dams.




Each of the stakes in the picture is offset from a corner of the building delineating one of the north-side rooms - from the right, the master bedroom, bathroom, computer/office area and laundry/utility room.

The hillside slopes to the southeast so even though the north side of each room in turn comes closer to the building's south side, the top of the back wall of each one isn't very much below the one to its east. This will help make the building less visible from up the hill toward the barn.

We are designing the ponds as we go since we had no practical way to gauge how much soil would need to be moved and be available for the pond. The plan is to have two ponds: a smaller one to allow dirt and debris to settle out, above a larger one that will be deep enough for wading. The soil is probably 90% clay so I may not have to install a liner in the ponds at all.

The soil near the front center of the building is soft. We are not quite down to the finished floor level so it may turn out OK. Going deeper to get to solid soil is not possible as that would also lower the rest of the building. Since the back wall is approaching the top of the nine foot wall already, lowering the entire floor would bring us below the soil level. And we can't lower the uphill soil level more than inches or we would have to shave the same depth all the way up the hill or install an expensive retaining wall across the entire north side.

It's getting late again. More tomorrow.

Monday, November 9, 2009

I feel the earth move under my feet...


We have finally started excavating for the new home. We've had a string of nice days and it looks like at worst we'll have just a bit of rain tomorrow and then some more nice days. If all goes well we'll have the site excavated and leveled for footing forms, and the ponds done by the end of the week.

Here are a few pictures showing the first day's progress. I tried to upload a video but it failed. I'll keep trying but it's getting late.


No, we aren't building another driveway. What you see is the track along which earth from the excavation is being pushed downhill to build two connected ponds.


Tomorrow we'll place corner stakes that include the extra 3 feet all the way around that the concrete guys need to get their forms in and out.

Thursday, November 5, 2009

Fall colors panorama


This video was taken on October 24th, when the trees were showing their best colors. It was taken from the highest point on Greene View Springs and pans from north to south.



All of the low land to the east and south, most of it unseen over the hillside, is in the American Bottoms.

Wednesday, November 4, 2009

Keep your mouth shut


For a week or so in late October and early November, the air near the apartment is filled with ladybugs. Well actually they are "multicolored Asian lady beetles," scientific name – Harmonia axyridis (Pallas). It seems they have virtually displaced our common ladybug, and these gals bite if you allow them to stay on you long enough.

Here's a picture of them on the outside wall, and then from the inside. They are often even more numerous. It is difficult to work near the barn when they are flying.




The foil and clothespin are used to keep the heat out of the barn on hot sunny days.

Here's just a brief idea of what it's like with them crawling around by the thousands looking for a place to hide for the winter.

Fall pictures


These speak for themselves...

This year's baby


Two years running the downy woodpeckers have raised a male baby, in this picture sitting in the persimmon tree by the window asking,"Where's the suet?"

Watch where you step


Almost exactly a year ago I posted some pictures of crayfish holes. I thought they were pretty big. Last week I found the granddaddy of them all almost at the highest point on the property. Here's what it looked like. I didn't leave the quarter there long for fear it would come out and take it.